The chute shaft was replaced during this year's overhaul of combustion line 4. The box-type feeder side walls filled with concrete were delivered ready for installation and placed onto the base structure. The chute shaft was lined with bolt-on wear plates. The cooling system for the chute shaft was adjusted to the new water circuit.
The work was completed on schedule and to the entire satisfaction of the client.